Reference document

Airspace authorization around DFW

Most of the Dallas metro sits under controlled airspace, so most construction sites here need authorization before anything flies. This is how that works, what it costs you in schedule, and where it gets hard.

This page describes how the system works, not what any particular grid reads today. The FAA revises UAS Facility Map ceilings on its own cycle, so a specific altitude published here would eventually be wrong — and a contractor scheduling against a stale number is exactly what this page exists to prevent. Send us the site address and you get the current ceiling for it, checked the day we quote.
§1

Airspace classes in the service area

Airspace classes, where they apply, ceilings and authorization path
ClassWhereTypical ceilingAuthorization pathTime
Class BDFW International · Dallas Love Field0–400 ft AGL, by gridLAANC, or an FAA DroneZone authorization where the grid reads 0Minutes — or plan 60 days on a zero grid
Class DAddison · Denton · McKinney · Arlington · Grand Prairie · Meacham · Alliance · Spinks · Tyler Pounds · North Texas RegionalVaries by grid, commonly 100–400 ft AGLLAANCMinutes
Class E surfaceNon-towered fields with instrument approaches to the surfaceVaries by gridLAANC where the field is mappedMinutes
Class GMost of the rural service area — including Rockwall, which is non-towered400 ft AGL (Part 107 limit)No authorization requiredNone

Class G covers most of the rural half of the service area. Class B is the one that actually affects scheduling.

§2

How grid ceilings work

The FAA publishes a UAS Facility Map that divides controlled airspace into one-mile grids, each with a maximum altitude that LAANC will approve automatically. Two sites a mile apart can have very different ceilings, which is why “can you fly here” is answered by the grid, not by the airport.

A grid reading zero does not mean flight is impossible. It means automatic approval isn’t available and a further FAA authorization is required — which is a schedule problem, not a technical one.

Example grid ceilings and what each means in practice
GridPublished ceilingWhat it means for your site
Zero grid0 ftNo LAANC. Needs an FAA DroneZone authorization, and Part 107 pilots only.
Runway corridor50–100 ftAuto-approved, but usually too low to map from. We fly it or tell you we can't.
Inner shelf200 ftAuto-approved and above normal mapping altitude for most sites.
Outer shelf300–400 ftAuto-approved. No practical constraint on the flight plan.
Uncontrolled400 ftPart 107 ceiling applies; no authorization needed at all.
§3

When a waiver is actually needed

Part 107 rules that may require a waiver and when they apply
RuleWhen it comes upPathIn practice
§107.51(b) — 400 ft AGLTall structures or terrain requiring higher flightWaiverRarely needed for mapping
§107.29 — night operationsFlights after civil twilightNow permitted with lightingNo waiver since the 2021 rule
§107.31 — visual line of sightLong corridors beyond VLOSWaiverCorridor work is flown in segments instead
§107.39 — over peopleActive sites with crews belowCategory rules or waiverUsually solved by scheduling, not paperwork

Most mapping work needs no waiver at all. Corridors and sites with tall structures are the exceptions worth flagging early.

§4

What airspace costs you in schedule

LAANC grid, non-zero ceiling

Minutes. No effect on the schedule at all — this covers most sites.

Zero-ceiling grid

FAA asks for 60 days on a DroneZone authorization. This is the one case where the site address has to reach us at bid time, not flight time.

Uncontrolled airspace

Nothing to file. The schedule is driven entirely by weather.

Airspace questions

§ FAQ
Can you fly inside the DFW Class B shelf?
Yes, in most grids. LAANC returns an automatic authorization up to the ceiling published for that grid, which is usually well above normal mapping altitude. Grids reading zero need an FAA authorization, which takes longer and has to be planned for.
How long does authorization take?
LAANC is typically minutes — it is an automated check against the grid ceiling. A zero-ceiling grid is a different process: an airspace authorization filed through FAA DroneZone, which the FAA asks you to submit at least 60 days ahead. That is the entire reason the site address matters at bid time rather than at flight time.
Do I need to do anything for airspace?
No. Authorization is our responsibility and is included in the quote. What helps is giving us the site address early — it's the one thing that can add weeks to a schedule.
What about flying over an active jobsite?
It's routine, and it's a scheduling question more than a regulatory one. We coordinate the window with the superintendent so the flight happens when the crew isn't underneath it.

Send the site address early.

It's the one thing that can add weeks — everything else is measured in hours.